The Maltings rebuild in Berwick now costs £36m, up £7.7m, and the council's share rises from £2.8m to £7.5m. Cabinet decides on 6 October; reopening April 2029.

The plan to rebuild the Maltings theatre in Berwick now costs £36.0m. That is £7.7m more than the budget agreed a year ago. Northumberland County Council’s own share would rise from £2.8m to £7.5m, with part of it borrowed.

The figures are in a report to the council’s Cabinet, which meets on Tuesday 6 October (Berwick Maltings Theatre: Project Status). Cabinet is asked to back the extra money and send it to Full Council in November for the final say. If both agree, building work on Eastern Lane starts in November.

Where the money comes from

In October 2025, Cabinet approved a budget of £28,337,415 for the whole project. The report now forecasts £36,011,856. It splits the cost like this:

Part of the project Forecast cost
Mob Store, Berwick Barracks £1,340,953
Gymnasium, Berwick Barracks £1,311,411
Eastern Lane theatre £33,359,492
Total £36,011,856

The £7,674,441 gap would be filled three ways:

  • £3.0m more from the Borderlands Inclusive Growth Deal. Its board approved the business case on 23 September and raised its grant from £25.5m to £28.5m. The extra £3m was moved from the deal’s digital programme.
  • £2.05m from the council’s Strategic Regeneration Projects budget. This includes £0.55m that had been set aside for the Berwick Visitor Gateway project.
  • £2.62m of new council borrowing. The report says this commits the council to debt charges of £0.241m a year, to be built into the February 2027 budget.

The council would then be paying £7.512m, or 21% of the cost. Borderlands would pay the other 79%.

Bar chart comparing the Berwick Maltings project in October 2025 and October 2026. Total cost rises from 28.34 million pounds to 36.01 million pounds. The council's share rises from 2.84 million pounds to 7.51 million pounds.
Chart by The Northumberland Post. Source: Northumberland County Council Cabinet report, 6 October 2026, tables 1 and 2.
Share this chartFacebookWhatsAppX

Why it went up

The report gives four reasons:

  • Inflation. It blames the conflict in the Middle East and tariffs on steel prices, which ran past the allowances in the original estimate.
  • A longer build. Surveys inside the building changed the plan. The construction programme went from 89 weeks to 109 weeks.
  • The setting. The Maltings sits in Berwick’s conservation area among listed buildings, so it needs high-quality outside materials.
  • Few local bidders. Some work packages drew little competition. An independent cost consultant said many subcontractors would have to come from south east Northumberland, Tyneside or Scotland, which pushes prices up.

The cost on the Gymnasium at the Barracks also rose after unforeseen work turned up during construction.

The report says the design team saved money by keeping more of the old building. Earlier designs gutted almost everything behind the outer walls. The current one reuses as much of the existing structure as it can. The building dates from the early 1800s and is not listed.

What Berwick would get

Willmott Dixon would build it under a contract worth £28.575m. The new Maltings would have:

  • a 289-seat theatre with flexible seating
  • two cinema screens, with 127 and 48 seats
  • a studio and rehearsal space
  • a café and bistro with views over the River Tweed
  • a new public entrance on the south side
  • solar panels, heat recovery ventilation and better insulation

The main point is to split theatre and film. Today they share one auditorium, which the report calls a “direct constraint” on how much the venue can put on. The business case forecasts 115,000 visitors a year and 61 new full-time jobs.

The other options

The report sets out what happens if councillors say no. None of them is free:

  • Patch up the damage from the surveys: roughly £3.34m.
  • A general refurbishment: roughly £11.64m, with no new layout.
  • Retender the job: no guarantee of a lower price, and a long delay.

The report says neither repair option would attract Borderlands money, so the council would pay the whole bill. Saying no outright would also put the £28.5m grant at risk.

When it would happen

The report’s timetable, if both votes go through:

Step When
Cabinet decision 6 October 2026
Full Council decision November 2026
Construction November 2026 to December 2028
Commissioning and test performances January to March 2029
Opening April 2029

The council’s announcement of 28 September says preliminary works would start before Christmas. Only a limited number of spaces in the Eastern Lane car park would be lost then. The main works would start in the new year.

What it means for you

  • The Maltings is still running. While Eastern Lane is shut, its programme moves to two buildings at Berwick Barracks. The Mob Store is already open as a temporary cinema. Work on the Gymnasium started in May and is due to finish in January 2027.
  • Eastern Lane car park loses some spaces from before Christmas. The council has not said how many. Our parking guide lists the alternatives.
  • Council tax payers would carry £0.241m a year in new debt charges. The report also warns that the Maltings (Berwick) Trust may need extra running money in 2027-28 because the build is longer. That would be decided in next year’s budget.
  • Want a say? Cabinet meets at 10am on 6 October and the agenda is public. Your county councillor votes at Full Council in November.

We will report the Cabinet decision.